[graphic][merged small][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed]

*FY 2003 Actual represents total obligations of funds incurred in FY 2003, irrespective of the year of appropriation

BG-8 of 8

CAPITOL VISITOR CENTER

ARCHITECT OF THE CAPITOL

Capitol Visitor Center

7793

INTRODUCTION

The appropriation previously provided funding for the construction of the Capitol Visitor Center (CVC). This Fiscal Year 2005 budget request provides funds for the operation, administration, and facility management that will support the required activities and programs for the following line items: transitional and stand-up costs, guide services, visitor services, exhibits, food services, and gift shops that impact the operation of the CVC Facility. In addition, the request for funding is being recommended by the Capitol Preservation Commission members (CPC) and is based on the U.S. Capitol Visitor Center Master Operations Plan provided by JM Zell Partners.

SIGNIFICANT CHANGES

Significant changes supporting for the operations of the CVC include the following: Transition Support ($2,400,000); Gift Shop ($1,200,000); and Visitor Services Support ($1,000,000).

FULL-TIME EQUIVALENT REQUIREMENTS

The FY 2005 FTE requirement contained in the below table reflects an increase of 16 FTEs over the FY 2004 level of 16.

[blocks in formation]

THE CAPITOL

CAPITOL VISITOR CENTER FY 2005 BUDGET

The Fiscal Year 2005 CVC Budget consists of an annual budget and a multi-year budget which are summarized in the following table:

[blocks in formation]

The increase of 16 FTEs is to support the new emerging CVC facility.
Specifically, the increase of 16 FTEs comprises of nine FTEs to provide
support for the Visitor Services; five FTEs for the Exhibits Gallery support;
and two FTEs for construction project support.

ANNUAL BUDGET

The FY 2005 annual budget request for the Capitol Visitor Center is $1,594,000, which is a $1,307,000 increase above the FY 2004 budget of $287,000. The annual budget consists of recurring payroll costs associated with the stand-up of this facility. The justification for the proposed increase in the recurring CVC annual budget for FY 2005 is provided in the section titled, "Analysis of Change."

[graphic]

MULTI-YEAR BUDGET

The FY 2005 multi-year budget request is $6,875,000. The basis for this multi-year budget plan is the result of the CVC Master Operations Plan provided by J.M. Zell Partners and recommended by the Capitol Preservation Commission (CPC). This plan is the main source of funding documentation that formulates the FY 2005 multi-year budget request for the CVC. Also included in this budget request is the U. S. Capitol Police request of $800,000 to support their CVC facilities build-out. Descriptions and justifications for the FY 2005 multi-year budget request can be found in the section titled, "Analysis of Change.fleet C22

CVC-1 of 6

[graphic][graphic]

Program Groups

Payroll (PR)
Total

CAPITOL VISITOR CENTER DETAILED FY 2004 BUDGET (S)

[blocks in formation]
[blocks in formation]
[graphic][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed]

Payroll (PR)
Increase Requested

ram Increases - Annual Recurring

$1,594,000 $1,305,000

Increase necessitated by an annual rise in mandatory and pay related
costs ($55,000) and the additional 16 FTEs supporting the CVC start-up
activities and project support ($1,250,000). A discussion regarding the
additional 16 FTEs can be found in the Architect of the Capitol General
Statement.

Transition Support

ogram Increases-Mult-Year

$2,400,000

This funding will provide support for the transitional cost associated
with the CVC services activity requirements for the operational
readiness upon pre-opening and opening of this facility. This activity
includes the art program, commissioning artwork, furniture, wayfinding
support, and training support to meet the needs of the CVC facility.
Impact if not funded: The ability to transition the CVC for operational
readiness will be adversely affected or not be met. FTE Impact: None.
Visitor Services

$1,000,000

This funding will provide support for the CVC Visitor Service by
providing information stations/pass desks, furnishing, ticketing system,
training supplies, and exterior pass distribution kiosks. Impact if not
funded: Inability to properly outfit the visitor services staff that will be
required for the opening of the CVC. FTE Impact: FTE requirements
are incorporated in the CVC FY 2005 budget request for an additional
nine FTEs.

USCP CVC Fit-Out

$800,000

This project will provide funding necessary for the fit-out of the U.S.
Capitol Police (USCP) assigned space (18,000 square feet) in the CVC.
Impact if not funded: USCP will be unable to utilize assigned CVC
space. FTE Impact: This project will be completed within the existing
FTE cap.

Gift Shops (Case work)

$1,200,000

This funding will provide for the planning and preparation of the gift shop display case work needed to meet the CVC requirements. Impact if not funded: The ability to prepare the gift shop(s) for the opening of the CVC will not be met. FTE Impact: This project will be completed within the existing FTE cap.

Administrative Support

$650,000

This funding will provide support for the procurement of administrative
equipment and furnishings, to include A/V equipment, furnishing for
meeting rooms, computers and office equipment. Impact if not funded:
The requisite administrative support will not be available for the
opening of the CVC. FTE Impact: None

Exhibits

$425,000

This funding will provide planning and preparation for the main hall
exhibits relating to theaters in the gallery, exhibit general storage space,
and electronic support operations meeting the needs of the CVC. The
exhibit gallery will include various state exhibits, Capitol images,
famous historical figures, etc. Impact if not funded: The ability to plan
and develop the CVC operational requirements for the main hall
exhibits will not be met. FTE Impact: FTE requirements are
incorporated in the CVC FY 2005 budget request for an additional five
FTEs.

[graphic]