(R 7-602.44(b) 1968 APR)

52.212-4 Liquidated

Damages-Supplies, Services, or Research and Development.

As prescribed in 12.204(a), the contracting officer may insert the following clause in solicitations and contracts when a fixed-price contract is contemplated for supplies, services, or research and development (see 12.202): LIQUIDATED DAMAGES-SUPPLIES,

SERVICES, OR RESEARCH AND DE-
VELOPMENT (APR 1984)

(a) If the Contractor fails to deliver the supplies or perform the services within the time specified in this contract, or any extension, the Contractor shall, in place of actual damages, pay to the Government as fixed, agreed, and liquidated damages, for each calendar day of delay the sum of [Contracting Officer insert amount].

(b) Alternatively, if delivery or performance is so delayed, the Government may terminate this contract in whole or in part under the Termination for Default-Supplies and Services clause in this contract and in that event, the Contractor shall be liable for fixed, agreed, and liquidated damages accruing until the time the Government may reasonably obtain delivery or performance of similar supplies or services. The liquidated damages shall be in addition to excess costs under the Termination clause.

(c) The Contractor shall not be charged with liquidated damages when the delay in delivery or performance arises out of causes beyond the control and without the fault or negligence of the Contractor as defined in the Termination for Default-Supplies and Services clause in this contract.

(End of clause)

(R 7-105.5 1969 AUG)

52.212-5 Liquidated Damages-Construction.

As prescribed in 12.204(b), the contracting officer may insert the following clause in solicitations and contracts for construction, except contracts on a cost-plus-fixed-fee basis (see 12.202):

LIQUIDATED DAMAGES-
CONSTRUCTION (APR 1984)

(a) If the Contractor fails to complete the work within the time specified in the contract, or any extension, the Contractor shall pay to the Government as liquidated damages, the sum of [Contracting Offi

cer insert amount] for each day of delay.

(b) If the Government terminates the Contractor's right to proceed, the resulting damage will consist of liquidated damages until such reasonable time as may be required for final completion of the work together with any increased costs occasioned the Government in completing the work.

(c) If the Government does not terminate the Contractor's right to proceed, the resulting damage will consist of liquidated damages until the work is completed or accepted.

(End of clause)

(R 7-602.5 1969 AUG)

(R 1-18.110(a))

(R 7-603.39 1965 JAN)

(R 1-8.709-1)

Alternate I (APR 1984). If different completion dates are specified in the contract for separate parts or stages of the work, revise paragraph (a) of the clause to state the amount of liquidated damages for delay of each separate part or stage of the work.

(R 7-603.39 1977 NOV)

52.212-6 Time Extensions.

As prescribed in 12.204(c), insert the following clause in solicitations and contracts for construction in which the clause at 52.212-5, Liquidated Damages-Construction, is used with its Alternate I:

TIME EXTENSIONS (APR 1984) Notwithstanding any other provisions of this contract, it is mutually understood that the time extensions for changes in the work will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements so delayed and that the remaining contract completion dates for all other portions of the work will not be altered and may further provide for an equitable readjustment of liquidated damages under the new completion schedule.

(End of clause)

(AV 7-603.36 1965 JAN)

52.212-7 Notice of Priority Rating for National Defense Use.

As prescribed in 12.304(a), insert the following provision:

NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE USE (MAY 1986)

Any contract awarded as a result of this solicitation will be a [ ] DX rated order; [ 1 DO rated order certified for national defense use under the Defense Priorities and Allocations System (DPAS) (15 CFR Part 350), and the Contractor will be required to follow all of the requirements of this regulation. [Contracting Officer check appropriate box.]

(End of provision)

[51 FR 19717, May 30, 1986]

52.212-8 Defense Priority and Allocation Requirements.

As prescribed in 12.304(b), insert the following clause:

DEFENSE PRIORITY AND ALLOCATION REQUIREMENTS (MAY 1986)

This is a rated order certified for national defense use, and the Contractor shall follow all the requirements of the Defense Priorities and Allocations System regulation (15 CFR Part 350).

(End of clause)

[51 FR 19717, May 30, 1986]

52.212-9 Variation in Quantity.

As prescribed in 12.403(a), insert the following clause in solicitations and contracts when a fixed-price contract is contemplated for supplies, and for services that involve the furnishing of supplies:

VARIATION IN QUANTITY (APR 1984)

(a) A variation in the quantity of any item called for by this contract will not be accepted unless the variation has been caused by conditions of loading, shipping, or packing, or allowances in manufacturing processes, and then only to the extent, if any, specified in paragraph (b) below.

(b) The permissible variation shall be limited to:

Percent increase [Contracting Officer insert percentage]

Percent decrease [Contract

ing Officer insert percentage]

This increase or decrease shall apply to

(End of clause)

(R 7-103.4(a) 1949 JUL)

(R 7-103.4(b) 1965 APR)

*Contracting Officer shall insert in the blank the designation(s) to which the percentages apply, such as (1) the total contract quantity, (2) item 1 only, (3) each quantity specified in the delivery schedule, (4) the total item quantity for each destination, or (5) the total quantity of each item without regard to destination.

52.212-10 Delivery of Excess Quantities of $100 or Less.

As prescribed in 12.403(b), the contracting officer may insert the following clause in solicitations and contracts, when a fixed-price supply contract is contemplated.

DELIVERY OF EXCESS QUANTITIES OF $100 OR LESS (APR 1984)

The Contractor is responsible for the delivery of each item quantity within allowable variations, if any. If the Contractor delivers and the Government receives quantities of any item in excess of the quantity called for (after considering any allowable variation in quantity), such excess quantities will be treated as being delivered for the convenience of the Contractor. The Government may retain such excess quantities up to $100 in value without compensating the Contractor therefor, and the Contractor waives all right, title, or interests therein. Quantities in excess of $100 will, at the option of the Government, either be returned at the Contractor's expense or retained and paid for by the Government at the contract unit price.

(End of clause)

(V 7-104.103 1980 DEC)

52.212-11 Variation in Estimated Quantity.

As prescribed in 12.403(c), insert the following clause in solicitations and contracts when a fixed-price construction contract is contemplated that authorizes a variation in the estimated quantity of unit-priced items:

VARIATION IN ESTIMATED QUANTITY (APR 1984)

If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.

(End of clause)

(R 7-603.27 1968 APR)

52.212-12 Suspension of Work.

As prescribed in 12.505(a), insert the following clause in solicitations and contracts when a fixed-price construction or architect-engineer contract is contemplated:

SUSPENSION OF WORK (APR 1984)

(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.

(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer's failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negli

gence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.

(c) A claim under this clause shall not be allowed (1) for any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order), and (2) unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.

(End of clause)

(R 7-602.46 1968 FEB)

52.212-13 Stop-Work Order.

As prescribed in 12.505(b), insert the following clause. The "90-day" period stated in the clause may be reduced to less than 90 days.

STOP-WORK ORDER (APR 1984)

(a) The Contracting Officer may, at any time, by written order to the Contractor, require the Contractor to stop all, or any part, of the work called for by this contract for a period of 90 days after the order is delivered to the Contractor, and for any further period to which the parties may agree. The order shall be specifically identified as a stop-work order issued under this clause. Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. Within a period of 90 days after a stop-work order is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, the Contracting Officer shall either

(1) Cancel the stop-work order; or

(2) Terminate the work covered by the order as provided in the Default, or the Termination for Convenience of the Government, clause of this contract.

(b) If a stop-work order issued under this clause is canceled or the period of the order or any extension thereof expires, the Contractor shall resume work. The Contracting Officer shall make an equitable adjustment in the delivery schedule or contract price, or both, and the contract shall be modified, in writing, accordingly, if—

(1) The stop-work order results in an increase in the time required for, or in the Contractor's cost properly allocable to, the performance of any part of this contract;

and

(2) The Contractor asserts a claim for the adjustment within 30 days after the end of the period of work stoppage; provided, that, if the Contracting Officer decides the facts justify the action, the Contracting Officer may receive and act upon the claim asserted at any time before final payment under this contract.

(c) If a stop-work order is not canceled and the work covered by the order is terminated for the conveninece of the Government, the Contracting Officer shall allow reasonable costs resulting from the stopwork order in arriving at the termination settlement.

(d) If a stop-work order is not canceled and the work covered by the order is terminated for default, the Contracting Officer shall allow, by equitable adjustment or otherwise, reasonable costs resulting from the stop-work order.

(End of clause)

(AV 7-105.3 1971 APR)

Alternate I (APR 1984). If this clause is inserted in a cost-reimbursement contract, substitute in paragraph (a)(2) the words "the Termination clause of this contract" for the words "the Default, or the Termination for Convenience of the Government clause of this contract." In paragraph (b) substitute the words "an equitable adjustment in the delivery schedule, the estimated cost, the fee, or a combination thereof, and in any other terms of the contract that may be affected" for the words "an equitable adjustment in the delivery schedule or contract price, or both."

[48 FR 42478, Sept. 19, 1983, as amended at 50 FR 2272, Jan. 15, 1985]

52.212-14 Stop-Work Order-Facilities.

As prescribed in 12.505(c), insert the following clause in solicitations and contracts when a facilities acquisition contract or a consolidated facilities contract is contemplated. The "90day" period stated in the clause may be reduced to less than 90 days.

STOP-WORK ORDER-FACILITIES

(APR 1984)

(a) The Contracting Officer may, at any time, by written order to the Contractor, require the Contractor to stop all, or any part, of the acquisition, construction, or installation work called for by this contract for a period of 90 days after the order is delivered to the Contractor, and for any further

period to which the parties may agree. The order shall be specifically identified as a stop-work order issued under this clause. Upon receipt of the order, the Contractor shall, at Government expense, immediately comply with its terms and take all reasonable steps to minimize the incurrence of cost allocable to the work covered by the order during the period of work stoppage. Within a period of 90 days after a stop-work order is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, the Contracting Officer shall either

(1) Cancel the stop-work order; or

(2) Terminate the work covered by the order as provided in the Termination of Work clause of this contract.

(b) If a stop-work order issued under this clause is canceled or the period of the order or any extension thereof expires, the Contractor shall resume work. The Contracting Officer shall make an equitable adjustment in the delivery completion schedule, the estimated cost, or both, and the contract shall be modified, in writing, accordingly, if—

(1) The stop-work order results in an increase in the time required for, or in the Contractor's cost properly allocable to, the performance of any part of this contract;

and

(2) The Contractor asserts a claim for the adjustment within 30 days after the end of the period of work stoppage; provided, that, if the Contracting Officer decides the facts justify the action, the Contracting Officer may receive and act upon the claim asserted at any time before final payment under this contract.

(c) If a stop-work order is not canceled and the work covered by the order is terminated, the Contracting Officer shall allow reasonable costs resulting from the stopwork order in arriving at the termination settlement.

(d) An appropriate equitable adjustment may be made in any related contract of the Contractor that provides for adjustment and is affected by any stop-work order under this clause. The Government shall not be liable to the Contractor for damages or loss of profits because of a stop-work order issued under this clause.

(End of clause)

(AV 7-702.21(d) 1964 SEP)

52.212-15 Government Delay of Work.

As prescribed in 12.505(d), insert the following clause in solicitations and contracts when a fixed-price contract is contemplated for supplies other than commercial or modified-commercial items. The clause use is optional

when a fixed-price contract is contemplated for services, or for supplies that are commercial or modified-commercial items.

GOVERNMENT DELAY OF WORK (APR

1984)

(a) If the performance of all or any part of the work of this contract is delayed or interrupted (1) by an act of the Contracting Officer in the administration of this contract that is not expressly or impliedly authorized by this contract, or (2) by a failure of the Contracting Officer to act within the time specified in this contract, or within a reasonable time if not specified, an adjustment (excluding profit) shall be made for any increase in the cost of performance of this contract caused by the delay or interruption and the contract shall be modified in writing accordingly. Adjustment shall also be made in the delivery or performance dates and any other contractual term or condition affected by the delay or interruption. However, no adjustment shall be made under this clause for any delay or interruption to the extent that performance would have been delayed or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an adjustment is provided or excluded under any other term or condition of this contract.

(b) A claim under this clause shall not be allowed (1) for any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved, and (2) unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the delay or interruption, but not later than the day of final payment under the contract.

(End of clause)

(AV 7-104.77 1968 SEP)

52.213-1 Fast Payment Procedure. As prescribed in 13.305, insert the following clause:

FAST PAYMENT PROCEDURE (AUG

1988)

(a) General. Invoices will be paid on the basis of the Contractor's delivery to a post office or common carrier (or, in shipment by other means, to the point of first receipt by the Government).

(b) Responsibility for supplies. Title to the supplies shall vest in the Government upon delivery to a post office or common carrier for shipment to the specific destination. If shipment is by means other than Postal Service or common carrier, title to the supplies shall vest in the Government upon de

livery to the point of first receipt by the Government. Notwithstanding any other provision of the contract, order, or blanket purchase agreement, the Contractor shall assume all responsibility and risk of loss for supplies (1) not received at destination, (2) damaged in transit, or (3) not conforming to purchase requirements. The Contractor shall either replace, repair, or correct those supplies promptly at the Contractor's expense, but only if instructions to do so are furnished by the Contracting Officer within 180 days from the date title to the supplies vests in the Government.

(c) Preparation of invoice. (1) Upon delivery of supplies to a post office or common carrier, (or, in shipments by other means, the point of first receipt by the Government) the Contractor shall prepare an invoice as provided in this contract, order, or blanket purchase agreement. In addition, the invoice shall be prominently marked "FAST PAY".

(2) If the purchase price excludes the cost of transportation, the Contractor shall enter the prepaid shipping cost on the invoice as a separate item. The cost of parcel post insurance will not be paid by the Government. If transportation charges are separately stated on the invoice, the Contractor agrees to retain related paid freight bills or other transportation billings paid separately for a period of 3 years and to furnish the bills to the Government when requested for audit purposes.

(3) If this contract, order, or blanket purchase agreement requires the preparation of a receiving report on a prescribed form, the Contractor has the option of either preparing the receiving report on the prescribed form or including the following information on the invoice, in addition to that required in subparagraph (c)(1) above:

(i) A statement in prominent letters "NO RECEIVING REPORT PREPARED”.

(ii) Shipment number. (iii) Mode of shipment.

(iv) At line item level, (A) national stock number and/or manufacturer's part number, (B) unit of measure, (C) Ship-To Point, (D) Mark-For Point if in contract, and (E) FEDSTRIP/MILSTRIP document number if in contract.

(4) If this contract, order or blanket purchase agreement does not require preparation of a receiving report on a prescribed form, the invoice will include at the line item level information at the line item level in addition to that required in subparagraph (c)(1) above:

(i) Ship-To-Point. (ii) Mark-For-Point. (iii) FEDSTRIP/MILSTRIP number if in contract, in addition to that required in subparagraph (c)(1) above.

document